It’s going to be a tight schedule, but in eight weeks the school rooms should be fully restored, some members of Stone Edge were even working on site this morning (Saturday) in order to keep within the time frame for completion. April was a busy month and May should prove even busier. High level work is progressing well, as in the re-pointed gable as shown in the picture so that the scaffolding can be taken down as soon as possible. The upper semi circular windows in the hall are in a poor condition and some are being replaced as they are beyond repair . More windows are being glazed on a daily basis and are looking fantastic. As sponsored windows have been glazed, sponsors have been sent photographs. It is not too late for you to sponsor a window. Now the weather has improved and the temperature has increased, the lime render is being applied.